A place to put all the information we can find about the East Post Bridge project that was on the books for years... construction began 3/15/2010 and is scheduled to be done in October (7 months).
Tuesday, March 30, 2010
Tuesday 3/30/10
Footings are being poured today! Not too much has changed at the bridge visually the last few days, hence no new pictures, but maybe this evening...
Thursday, March 25, 2010
3/25/10
New pipes. Craig said they are still having trouble getting bearing.
they've added and added, but still haven't hit bedrock in some areas...
they've added and added, but still haven't hit bedrock in some areas...
Tuesday, March 23, 2010
3/23/10 progress
"We didn't get bearing" - Craig, structural foreman. but it wasn't a
total bad day, because they did get a lot in.
total bad day, because they did get a lot in.
Monday, March 22, 2010
Saturday, March 20, 2010
Thursday, March 18, 2010