A place to put all the information we can find about the East Post Bridge project that was on the books for years... construction began 3/15/2010 and is scheduled to be done in October (7 months).
Wednesday, October 20, 2010
Tuesday, October 19, 2010
pipe at the ready
It was quiet on the south side of the bridge this morning, the pipe has been assembled, will be bored under the west side of the road and under Indian Creek perhaps today?
Wednesday, October 13, 2010
New pipes
This is the new natural gas transmission line they will bore under the creek from south to north. The pipes stretch from Trailridge Rd to the power line right-of-way. There was also some pouring underway, some bridge finish work. Overall it is looking good!
Tuesday, October 12, 2010
Dusty morning
Great progress has been made - the bridge and road are now connected on both sides, the Kennelworth Court intersection is paved. Maxwell has been out finishing the storm sewer enclosures.
It seems doubtful the Maxwell folks tagged their work like this... not sure what to think of that. It appears to say "shitake", with a paw print through it.
Tuesday, October 5, 2010
Friday, October 1, 2010