Tuesday, October 19, 2010

North side action

Not sure what they are working on, but all the action was on the north side early this morning.

pipe at the ready

It was quiet on the south side of the bridge this morning, the pipe has been assembled, will be bored under the west side of the road and under Indian Creek perhaps today?

Wednesday, October 13, 2010

New pipes

This is the new natural gas transmission line they will bore under the creek from south to north. The pipes stretch from Trailridge Rd to the power line right-of-way. There was also some pouring underway, some bridge finish work. Overall it is looking good!

Tuesday, October 12, 2010

Dusty morning

They were running the street sweeper this morning over the fresh pavement, raising dust like a soybean field harvest, quite lovely in the sunrise. 










Great progress has been made - the bridge and road are now connected on both sides, the Kennelworth Court intersection is paved. Maxwell has been out finishing the storm sewer enclosures.



It seems doubtful the Maxwell folks tagged their work like this... not sure what to think of that. It appears to say "shitake", with a paw print through it.