A place to put all the information we can find about the East Post Bridge project that was on the books for years... construction began 3/15/2010 and is scheduled to be done in October (7 months).
Thursday, September 9, 2010
Tuesday, September 7, 2010
9/7/10 muckiness
The muck pools in a large hole (sewer line install) on the south side of the construction zone this morning.
On the north side it looks like they're moving toward paving - there is a fresh layer of crushed stone. Also, painting of the bridge's faux stone has begun.
It might not look like it from this picture, but they seem to be nearing the home stretch!
Thursday, September 2, 2010
Another pour
Friday they will pour the final bridge segments- all 4 corners. They also plan on starting the staining tomorrow, neat-o!
Wednesday, September 1, 2010
Morning muck in the construction zone
It was a gooey morning... but they stayed at it all day. Sewer, water main and gas line work is going on now, which is the last big task before paving.
Looking forward to seeing the staining of the faux rock - should start on Friday.