This is the new storm sewer on the SE corner of the bridge. The hole is
about 20' deep. Water is already creeping up the pipe from the creek.
A place to put all the information we can find about the East Post Bridge project that was on the books for years... construction began 3/15/2010 and is scheduled to be done in October (7 months).
Wednesday, April 28, 2010
Friday, April 23, 2010
Wednesday, April 21, 2010
Tuesday, April 20, 2010
Saturday, April 17, 2010
4/17/10 7:45am
Daryl is poised to start ripping up some asphalt on the south side of
the bridge this morning. They moved the big yellow trailer and
generator to the north side, out of the way for the water line work.
the bridge this morning. They moved the big yellow trailer and
generator to the north side, out of the way for the water line work.