South side SB lane 5pm

They were just finishing spraying the SB lane with white stuff (anyone know what that is?). 3 days and the south side local traffic (Kennelworth Ct, 3 E Post households)will be routed back on to hard surface for the first time in what seems like forever.

New Road!

The Paver is hard at work laying new road - this morning they did the north side of the bridge, the SB lane; now they're working on the south side of the bridge. No traffic will be allowed for at least 3 days to allow for proper curing, and it will be walkable by this evening. Progress!

9/28/10 7:45am

Monday, September 27, 2010

9/27/10 Progress

The paver is now on site, work will begin on the southbound lane Tuesday morning. It will need 3 days to cure, then they will do the other side.

9/27/10 Green light

The lights on the bridge are LED, and will be a whiter light and energy efficient.

Thursday, September 23, 2010

9/23/10

The lamp posts are up! Otherwise, not much has changed this week.

Monday, September 20, 2010

Tuesday, September 7, 2010

paint job

9/7/10 muckiness

The muck pools in a large hole (sewer line install) on the south side of the construction zone this morning.

On the north side it looks like they're moving toward paving - there is a fresh layer of crushed stone. Also, painting of the bridge's faux stone has begun.

It might not look like it from this picture, but they seem to be nearing the home stretch!

Thursday, September 2, 2010

Another pour

Friday they will pour the final bridge segments- all 4 corners. They also plan on starting the staining tomorrow, neat-o!

North side roadway

Services work continues on the north side - including gas, storm sewer and water main.

Wednesday, September 1, 2010

Morning muck in the construction zone

It was a gooey morning... but they stayed at it all day. Sewer, water main and gas line work is going on now, which is the last big task before paving.

Looking forward to seeing the staining of the faux rock - should start on Friday.